| project_name |
uk_project_manager |
status |
| Chemotherapy Infusion Center Expansion (Diagnostic Services Upgrade VIII |
Sandy Redmon |
Phase 3 - Construction Documents=3 Phase 3/ 2nd time |
| Hospital Entrance Lobby Improvements |
Sandy Redmon |
Phase 5 - Construction Administration=5 |
| Hospital Interior Design Study |
Dall Clark |
Programming=0 |
Primary Care Ctr/Outpatient Diagnostic & Treatment (Center for Advanced
Surgery/Gill Heart)
|
David Collins |
Phase 5 - Construction Administration=5 |
| Renovation of Room CC038 for New Linear Accelerator |
Keith Ingram |
Warranty |